iGuide

Surveys You Need for a Dual Occupancy

A duplex needs a surveyor at several points, from the first design to the new titles. Here is every survey, in the order you will need them, and why each one matters.

5 min readBy Taha Abdo, Registered Surveyor SU010105

1. Detail and level survey, with boundaries

Your architect or designer can't start properly without it. The detail and level survey shows the existing house and outbuildings, levels and contours to AHD, trees, services, kerb and footpath levels, and the neighbouring buildings and windows. Most councils want it signed by a registered surveyor, and some set a maximum age at lodgement.

For a dual occupancy we recommend a boundary identification at the same time. Setbacks, lot widths and any future subdivision all depend on the real boundary, not the fence. Doing both in one visit saves a second trip.

2. Preliminary subdivision plan, if you will subdivide

If you plan to sell or finance the two dwellings separately, think about subdivision before the DA goes in. For a Torrens subdivision, a preliminary plan showing the proposed lots, areas and easements usually goes in with the DA or the complying development application. For strata, the design needs to suit the strata plan that will follow. Your planner will confirm what council needs.

3. Set out

Once you have approval and a construction certificate, the builder needs the building set out on the ground. The surveyor marks the building corners or offset lines from the approved plans and the boundaries, with a level reference to AHD so the builder can set the slab height. A mistake here is expensive later, so the set out should come from the same boundary work the design used.

4. Level and position checks during the build

Many certifiers and builders want checks at key stages, for example:

  • formwork or slab check before the pour, confirming position and floor level
  • frame or first floor check, confirming heights against the approved plans
  • retaining walls or driveways where levels are tight

These checks catch problems while they are still cheap to fix.

5. Final survey and work-as-executed

At the end of the build the certifier usually needs a final survey before issuing the occupation certificate. It shows the completed buildings in relation to the boundaries, and often key levels. Where there is on-site detention or other stormwater works, a work-as-executed survey shows what was actually built so the engineer can certify it.

6. Subdivision: strata or Torrens

With strata, the plan defines each dwelling as a lot and the shared areas as common property. The strata plan is drawn once the building is complete or substantially complete, because the council or registered certifier inspects the building and checks it against the plan before issuing a strata certificate.

With Torrens title, each dwelling sits on its own lot with its own boundaries. The final plan is surveyed and marked, connected to permanent survey marks, and needs a subdivision certificate. Either way, any easements or restrictions go in a section 88B instrument, and the plan is lodged online with NSW Land Registry Services. Which title suits you is a planning, legal and financial question, and we can explain the survey side of each.

Why one surveyor for the whole job helps

Each survey builds on the last. When the same surveyor does the detail survey, the set out, the checks, the final survey and the subdivision plan, the boundaries and levels stay consistent from start to finish. Nobody has to re-check another firm's work.

Tell us at the start if you plan to subdivide, and which title you are leaning towards. It changes what we pick up in the first survey and how we set out the building, and it avoids paying twice for the same boundary work. We give a fixed-fee quote for each stage, or for the whole sequence, so you know the survey costs before you commit. What drives the cost is mainly the site, the number of checks your certifier or builder wants, and the type of subdivision.

Get a quote

Send us the address.